Industrial / Carrickfergus

Kilroot Power Station

Bridge & GCB room removal

Dismantling of steel bridge structures and demolition of GCB rooms within an operational power station.

Steel bridge structure within Kilroot Power Station
01 / Understand

The challenge.

  • Live services included pressurised hydrogen lines.
  • Structural stability, work at height and lifting constraints shaped the sequence.
  • Plant movements and demolition areas needed coordination within the operating facility.
02 / Control & deliver

Harte’s solution.

  • Sequenced work around live services, with out-of-hours working to meet client requirements.
  • Dismantled and lowered three steel bridge structures using an overhead gantry crane.
  • Used engineered protection, temporary works and controlled exclusion zones.
The result

Delivery.

Three steel bridge structures and associated GCB-room elements removed within the planned demolition scope.