Healthcare / Huntingdon, Cambridgeshire

Hinchingbrooke Hospital

Staff accommodation · Phase 1

Soft strip and structural demolition of St Nicholas House and Albert House within a working hospital campus.

Original survey photograph of St Nicholas House staff accommodation at Hinchingbrooke Hospital
St Nicholas House before the works — original survey photograph.
01 / Understand

The challenge.

  • Hospital access and emergency routes needed to remain available.
  • Service isolations and asbestos removal had to precede demolition.
  • Dust, noise and vehicle movements needed control around hospital users.
02 / Control & deliver

Harte’s solution.

  • Coordinated service disconnections, asbestos removal and soft strip.
  • Carried out sequenced demolition with water suppression and material segregation.
  • Removed slabs and foundations, capped drainage and completed making good.
The result

Delivery.

Phase 1 completed for St Nicholas House, comprising three houses, and Albert House, comprising 12 apartments.