Controlled removal of a brick chimney, boilers and associated steelwork within a live hospital site.

Scaffolded brick chimney at Braid Valley Hospital
01 / Understand

The challenge.

  • Adjacent buildings required close monitoring during demolition.
  • Work at height called for a controlled top-down removal sequence.
  • Roof steelwork and tanks required planned lifting and safe handling.
02 / Control & deliver

Harte’s solution.

  • Planned chimney dismantling from scaffold using handheld breakers.
  • Reduced the scaffold in stages as the chimney came down.
  • Used crane lifts for steelwork and tanks, with controlled waste removal.
The result

Delivery.

Brick chimney, boilers, steel structures and associated walls removed safely and on time.