Industrial / Carrickfergus

Kilroot Power Station

Fuel tank removal

Removal of three redundant fuel tanks, D, E and F, within the West RUT bund, enabling new fuel-storage infrastructure.

Redundant steel fuel tanks at Kilroot Power Station
01 / Understand

The challenge.

  • The power station remained operational beside the work area.
  • The adjoining railway required strict control of plant movements and debris.
  • Restricted bund access and residual fuel contamination shaped the sequence.
02 / Control & deliver

Harte’s solution.

  • Coordinated tank cleaning, cladding removal and service removal before demolition.
  • Planned mechanical shearing in sequence, using a slew restrictor for Tank D beside the railway.
  • Retained the bund, segregated waste and planned final cleaning for the next stage.
The result

Delivery.

Three steel fuel tanks, associated services and base plates removed, with the bund retained for reuse.

Let’s discuss
your project.

Send us your scope, programme and site constraints. We’ll help plan a safe, practical route to delivery.