Dorchester House
Structural demolition of a multistorey reinforced concrete building as part of redevelopment into a 136-bed aparthotel.
01 / Understand
The challenge.
- A constrained urban site bordered neighbouring properties and public areas.
- Retained structures and existing services needed protection.
- Slabs, beams, columns and façade elements required a controlled removal sequence.
02 / Control & deliver
Harte’s solution.
- Planned floor-by-floor demolition supported by temporary works and controlled lifting.
- Used Brokk demolition, concrete cutting and mini excavators in restricted work areas.
- Coordinated crane operations, crash decks and designated drop zones to handle materials.
The result
Delivery.
Structural demolition sequenced around retained elements and the wider redevelopment.